LBJ Freeway opens with a capacity to handle 180,000 vehicles a day
2009
LBJ Freeway reaches a capacity of 270,000 vehicles per day;
Texas Department of Transportation awards LBJ Express development contract to LBJ Infrastructure Group LLC
2011
Construction begins on the LBJ Express project
June 2013
LBJ Express achieves 50% completion milestone
December 14, 2013
Phase 1 completed: I-635, from Preston Road to Greenville Avenue, opens
July 16, 2014
Completion of Phase 2: I-635, from Josey Lane onto I-35E south to the 35E/Loop 12 split and north before Valley View Lane
September 10, 2015
Completion of Phase 3: I-635, from Luna Road to Preston Road; entire roadway opens, connecting east and west sections of LBJ Express
2016
Commencement of service on completed LBJ Express
2061
LBJ Express returns to Texas Department of Transportation